Eastern region construction update and travel advisory

Jan. 17, 2020 - Jan. 31, 2020
WSDOT Eastern Region, 509-324-6000

2020 Eastern Region construction map (pdf 256 kb)

Please Note: All construction and maintenance activities are weather dependent. 

 

2019 Eastern Region Chip Seal
Highway: SR 20, 26 Region: Eastern County: Ferry, Stevens, Pend Oreille, Adams, and Whitman 
Description: Crack seal, prelevel areas, pavement repair areas, bridge deck repair, rumble strips, and guardrail.

  • Work Schedule: Project under suspension due to weather. The contractor will finish the fog seal next year. 

Contact: Chad Simonson, Project Engineer, 509-324-6252

Adams

Ferry

Keller Ferry Terminal and Pontoon Replacement North and South (MP 106.65 to 106.67)
Highway: SR 21 Region: Eastern County: Lincoln and Ferry Location: MP 106.65 to 106.67
Description: Construction to take place at the north and south Keller Ferry Terminals. Work will include replacing pontoons, decking, railing, and anchors.
Project Website: http://wsdot.wa.gov/projects/sr21/keller-ferry/home

  • Work Schedule: Substantial completion happened on October 1. No traffic control impacts at this time.

Contact: Chad Simonson, Project Engineer, 509-324-6252

SR 21 - West Fork Sanpoil Bridge Replace Structure (MP 145.6)
Highway: SR 21 Region: Eastern County: Ferry Location: MP 145.6
Description: Earthwork, removing and relocating the temporary Bailey Bridge, removing the existing bridge and installing a new bridge with wing walls, paving with HMA, stream channel excavation and in water stream work, rock and boulder placing, woody material placing and other items.
Project Website: https://www.wsdot.wa.gov/projects/sr21/westfork-san-poil-bridge/home

  • Work Schedule: Work has been suspended as of December 2.

Contact: Mark Allen, Project Engineer, 509-324-6232

Lincoln

Pend Oreille

Spokane

I-90 Medical Lake/SR 902 Interchange Improvements (MP 272.81)
Highway: I-90/SR 902 Region: Eastern County: Spokane Location: MP 272.81
Description: Reconstruction of the intersections at the eastbound and westbound ramp terminals. This will replace the current intersections with roundabouts. Replacement and relocation of the intersection of SR 902 and Geiger Blvd. with a roundabout. Construction of a new bridge structure parallel to the existing overpass at I-90.
Project Website: https://www.wsdot.wa.gov/projects/i90/medical-lake/home

  • Work Schedule: Work on the bridge is currently suspended. Forming of the new bridge deck will begin when the snow clears.

Contact: Mark Allen, Project Engineer, 509-324-6232

North Spokane Corridor-US 395/Freya Structures (MP 162)
Highway: US 395 Region: Eastern County: Spokane Location: NSC MP 162
Description: Construct two mainline freeway bridges over Freya Street.
Project Website: http://www.wsdot.wa.gov/Projects/US395/nspokanecorridorfreya/

  • Work Schedule: The contractor issued physical completion. 

Contact: Mark Allen, Project Engineer, 509-324-6232

North Spokane Corridor-US 395/Columbia to Freya (MP 161.1 to 162.3)
Highway: US 395 Region: Eastern County: Spokane Location: MP 161.1 to 162.3
Description: Construct mainline NSC from Freya to Columbia. Contaminated material has been excavated on the north end of the project and samples are waiting for final test results. Minor drainage work. Erosion control work as needed.
Project Website: https://www.wsdot.wa.gov/Projects/US395/columbiatofreya/default.htm

  • Work Schedule: Project is on suspension for the winter. Next season the contractor will install the barrier fence for the pedestrian path as well as finishing and painting the barrier.

Contact: Mark Allen, Project Engineer, 509-324-6232

North Spokane Corridor-US 395/NSC BNSF 2nd Railroad Realignment
Highway: US 395 Region: Eastern County: Spokane Location: NSC 
Description: Construction of two railroad structures, BNSF shoofly, retaining wall, clearing, and grubbing, roadway excavation and embankment, HMA paving, installing curb and sidewalk plus utility work.
Project Website: https://www.wsdot.wa.gov/projects/us395/nsc-bnsf/home

  • Work Schedule: The three-year closure of Wellesley Avenue began on Nov. 21, 2019. Clearing and grubbing will continue along with excavation and exporting of class four and class three material. Excavation, embankment and water work on Rockwell continues. The excavation of Wellesley, removal of the track and multiple retaining walls and concrete pours will take place.

Contact: Chad Simonson, Project Engineer, 509-324-6252

Spokane Area Traffic Volume Collection (MP 286.19 to 292.02)
Highway: I-90 Region: Eastern County: Spokane Location: MP 286.19 to MP 292.02
Description: Upgrades and adds to the existing traffic data accumulation system.

  • Work Schedule: All work for the project is now complete and physical completion has been granted. 

Contact: Tom Brasch, Project Engineer, 509-323-8411

Stevens

  • No scheduled traffic impacts

Whitman

PCC Railroad Structure Rehabilitation and Replacement
Highway: Near US 195 Region: Eastern County: Spokane & Whitman 
Description: Rehabilitate bridges at MP 10.5 & 28.4, replace bridge at MP 29.48 and replace bridge at MP 23.89 with a culvert.

  • Work Schedule: Punchlist items remain. Project under winter suspension until seeding window opens in spring.

Contact: Chad Simonson, Project Engineer, 509-324-6252

PV Hooper Track Improvements
Highway: Near SR 26 Region: Eastern County: Adams & Whitman 
Description: Hooper railroad line at MP 25.79 to 41.60. This project replaces ties, rail, and OTM, places ballast, track and restores ditches.

  • Work Schedule: Ballast distribution is weather dependant.

Contact: Chad Simonson, Project Engineer, 509-324-6252

 